Smiths Lane Branch Sewer Overview

Delplant was responsible for the construction of 6 metre deep 1.2km long 300mm Branch Sewer (PVC & GRP) including 28 sewer manhole structures.

Despite challenging site conditions including limited site access and poor ground conditions, Delplant successfully and safely delivered the project on time and on budget.

Project Details

Developer: Mirvac
Consultant: Beveridge Williams
Responsible Authorities: South East Water & APA
Services: Branch Sewer
Location: Clyde North
Project Commencement: September 2021
Project Duration: 3-4 months
Project Status: Complete
Value of works: $1,000,000